History: Brăila Bridge
Preview of version: 7
- «
- »
Carries: | Four lanes of roadway, two combined bicycle path and pedestrian walkways |
Crosses: | Danube |
Locale: | Between Brăila, Brăila County and Smârdan, Tulcea County |
Official name: | Suspended Bridge over the Danube in Brăila Area |
Design: | Suspension bridge |
Total length: | 2,194.3 m (7,199 ft) |
Width: | 31.7 m (104 ft) |
Height: | 192 m (630 ft) (towers) |
Longest span: | 1,120 m (3,670 ft) |
Clearance below: | 38 metres (125 ft) (at maximum high water) |
Constructed by: | Astaldi Romania and IHI Infrastructure Systems |
Construction start: | 2018 |
Construction end: | 2023 (planned) |
Construction cost: | ~ € 433 million |
The Brăila Bridge is a road suspension bridge in Romania, still under construction. The bridge crosses over the Danube river, between Brăila, a major city in the east of Romania, and the opposite bank of the river in Tulcea County. This will be the first bridge over the maritime Danube sector, and the fourth bridge over the Romanian section of the river. The bridge will improve road traffic accessibility of the Galați-Brăila area to Constanța and Tulcea, and connections between Moldavia, Muntenia and Dobruja regions.
Table of contents
History
- 2017 - The tender for the construction of the bridge is launched.
- 2017 - There were two associations that made offers for the construction of the bridge:
- Astaldi SpA - Romanian branch – IHI Infrastructure Systems Co. Ltd (Japan)
- China Communication Construction Company Ltd (China) – China Road and Bridge Corporation (China) – Eptisa Servicios de Ingenieria SL (Spain)– Euro Construct Trading '98 SRL (Romania)– CCCC Second Harbour Engineering Co Ltd) (China)- CCCC Highway Consults Co Ltd (China).
- 20 October 2017 - the contract to build the Brăila Bridge is awarded to the association between Astaldi Romania and IHI Infrastructure Systems for 1.995.932.260,25 lei (without VAT) (~ € 433 million) 1
Development
Construction milestones
- 2018 - Start of the construction works
- December 2020 - The pillars of the bridge reached their maximum height
Specifications
The project consists of the construction of a suspension bridge of 1,974.30 m (6,477.4 ft) length (with a 1,120 m (3,670 ft) main span, and two side spans of 489.65 m (1,606.5 ft) long on the Brăila bank of the river and 364.65 m (1,196.4 ft) long on the Tulcea bank of the river), two access viaducts of 110 m (360 ft) length on both sides (which will add to the length of the suspended bridge), and a connecting road with a total length of approximately 23 km (14 mi). The entire project is being built by the Astaldi (Romanian branch) and IHI Infrastructure Systems association, at an estimated cost of € 433 millionCurrent status
Under construction, expected to be opened in 2023Statistics
After it will be built the Brăila Bridge with its longest span of 1,120 m (3670 ft) will be in the top 5 bridges in EuropeFurther reading
Bridges in Romania
List of bridges in Romania
List of bridges in Europe
List of longest suspension bridge spans
Romania
Danube
History
Quick Edit a Wiki Page
Join us
Join our effort to create the best page about transportation, vehicles (ships, airplanes, trains, trucks, buses, etc.)
Register now and start editing!
Register now and start editing!